Beyond Surveying and Engineering
Construction Status

Janesville Road Reconstruction, Waukesha County

Updates

May 1, 2013

The contractor has been on site the last two weeks working on the final items to complete CTH “L” (Janesville Road) from Moorland Road to Lannon Road.  As you may have observed, this area has been restricted to one lane of traffic in each direction for the past several weeks and will continue to be restricted to one lane in each direction for the next several weeks.

On Monday, May 6, 2013, the contractor will be making another change to the traffic pattern on CTH  “L.” Beginning Monday, May 6, eastbound traffic at the intersections of Parkland and CTH “L” and Bay Lane and CTH “L” will be switched to the inside or median lane. This is being done to allow for the completion of the brick cross walks at Parkland and to allow for the contractor to complete the concrete pavement at the Bay Lane intersection.  

Traffic through the Parkland and CTH “L” intersection will still have unrestricted access to Parkland Dr. in both the eastbound and westbound directions.
Traffic through the Bay Lane and CTH “L” intersection will not be able to proceed south on Bay Lane beginning on Monday, May 6. This closure should last for approximately two weeks while the contractor completes the placement of the concrete pavement and the brick cross walks. Bay Lane can be accessed from either Martin Road or Bellview Road.     

While the contractor is working on the completion of the Parkland and Bay Lane intersections, they will continue to work on landscaping items throughout the project site. Because the landscaping areas are located throughout the length of the project, it is very difficult to provide accurate information as to where the contractor will be working at any given time. For this reason, we would again like to remind all traffic that the posted and enforceable speed limit on CTH “L” from Moorland Road to Lannon Road is 25 MPH. Also, please be aware that traffic patterns may be switched with little or no notice to accommodate the contactor’s completion schedule, so please exercise caution while driving through the work zone.

Once the work in the Parkland and Bay Lane intersections is completed, the contractor will be scheduling final adjustment of the storm sewer, water main and sanitary sewer structures that are in the pavement areas and will then work on the installation of the final layer of asphalt on the project.

The contractor is still on schedule to have all work on CTH “L” from Moorland to Lannon completed by the June 14, 2013, completion date.

If you have questions or concerns regarding the project, please do not hesitate to contact us. The field office is located at S73W16582 Janesville Rd; the field office telephone number is (414) 422-4751.   Please feel free to contact Mr. Mike Mentzel at mike.mentzel@rasmithnational.com, or by phone at 262-317-3338 with questions or concerns that you have.  You may also contact Mr. Ed Hinrichs of Waukesha County at 262-548-7740 or by e-mail at EHinrichs@waukeshacounty.gov.

Thank you in advance for your understanding of the delays that may occur as you travel through the construction zone.

  

[ Update Archive ]

About

R.A. Smith National, Inc. has been hired by Waukesha County to provide construction management services for the upcoming reconstruction of Janesville Road (CTH L).     

Mr. Mike Mentzel of R.A. SmithNational, Inc. has been assigned to the project as the Construction Project Engineer and will be providing information on this site concerning the construction schedule and plan starting in early 2012.  Mr. Mentzel can be reached by e-mail at Mike.Mentzel@RASMITHNATIONAL.com or by phone at 262-317-3338 with questions or concerns that you have regarding the construction of the project.

The project involves the total reconstruction of the section of Janesville Road from Moorland Road to Lannon Road and will involve the conversion of the roadway from a two lane road to a four lane road with a median.  Construction activities are tentatively expected to start in April/May of 2012 and be completed by mid November, 2012.  Detailed information concerning the construction activities will be provided on this site starting in late February, 2012 after a contractor has been hired by Waukesha County to construct the project.

While the actual reconstruction of Janesville Road is not beginning until spring of 2012, relocation of the existing gas, electric, telephone and cable television utilities out of the road reconstruction area is tentatively scheduled to start in mid to late October 2011.  The work is being performed by the utilities in question and is anticipated to last from October, 2011 until early spring of 2012.   

The utilities involved will be making direct contact with all affected residents and businesses to coordinate this work with them. If you have questions or concerns regarding the utility relocation work, please contact the appropriate utility representative. When the utilities representatives contact residents and businesses, they will also provide the respective contact information. 

Contact

If you are experiencing problems with the utility company representatives please contact either Mr. Ed Hinrichs of Waukesha County at 262-548-7740 or Mr. Mike Mentzel of R.A. Smith National and they will work with the utility to obtain an answer to your question.  

Share this:        Copyright R.A. Smith National, Inc., 1997-