Construction Status


60th Street Reconstruction, City of West Allis

Updates

August 22, 2011
Thank you for your understanding and cooperation during the reconstruction of S. 60th St. from National Ave. to the Henry Aaron Bike Trail to the north. On Wednesday, August 25, 2011, the contractor will be re-opening this section of the project to traffic.

While this section of the project will be open to traffic, the contractor will still be working in the area over the next several weeks to complete the following items:

  • Completion of the traffic signals at the intersection of Mineral St. and S. 60th St. Please exercise caution through this area as the traffic signal will not be operational for several weeks. Traffic on Mineral Street will be controlled by a stop sign, but please use extra caution in this area. When the traffic signals are made operational, they will be placed in a flashing operation for several days prior to being fully activated.
  • Completion of a retaining wall and the landscaping connected with the retaining wall from Walker St. to Pierce St. When this work is taking place, the contractor will close the northbound lane closest to the curb. Please be aware of traffic barrels and warning signs in this area.
  • Completion of the remaining sidewalk from Walker St. to the Henry Aaron Bike Trail Bridge. When this work is taking place, the contractor will close the northbound lane closest to the curb. Please be aware of traffic barrels and warning signs in this area.
  • There may also be clean-up and minor items that will require the contractor’s attention in this section of the road where only a portion of a lane may need to be closed for a short period of time. Once again, until all work is completed, your cooperation is appreciated and will speed the completion of the contractor’s work.

On Wednesday, August 25, when S. 60th Street is opened to the north, the contractor will be closing the intersection of Greenfield Ave and S. 60th Street to traffic to complete the work in this area. It is anticipated that the work in this area will take six to eight weeks with the contractor anticipating completion by October 18. A detour will be posted for this section of work starting on Wednesday morning, August 25.

During the completion of the work in the intersection of S. 60th St. and Greenfield Ave., access to Maas Petroleum should be made via S. 60th St. from the intersection of National and S. 60th St. This section of S. 60th Street will be open only to patrons of Maas Petroleum, and there will be no access available beyond Maas Petroleum.

Please do not attempt to travel through the work zone at the intersection of Greenfield and S. 60th St. for your safety and the safety of the construction crews. Your cooperation is greatly appreciated as it will make for a safer project and will allow the contractor to finish his work in a timely manner.

If you have questions or concerns regarding these activities or any other aspects of the project, please contact us at the project field office or via e-mail.

[ Update Archive ]

Assitance for Local Businesses

In This Together
Online Business Assistance Program

TogetherThe Wisconsin Department of Transportation (WisDOT) has created an online assistance program to assist businesses and community leaders in planning ahead for road construction. Click here for a variety of helpful resources, including an online workbook, case studies and promotional samples that demonstrate techniques that have been used successfully in communities throughout Wisconsin.


Contact

If you have specific questions concerning the project and how it affects you, please contact the construction project manager, Mike Mentzel of R.A. Smith National, Inc. Mike can be reached either by e-mail at mike.mentzel@rasmithnational.com or at the construction field office at 414-321-5040. Field office address is 6006 W. Lincoln Ave. in the City of West Allis.

Project History

R.A. Smith National, Inc. is again providing construction management service to the Wisconsin Department of Transportation for the second half of the reconstruction of 60th St. This years work will occur from National Ave. to approximately 200 feet north of Pierce St. in the City of West Allis.

The project involves the complete reconstruction of 60th St. including new pavement, traffic signals, street lights, and sanitary sewer, storm sewer and water utilities upgrades throughout the project area.

Work on the project, which involves three stages, will tentatively begin on April 6, 2011 and completed in November, 2011. To assist you in planning for this project, click here to view detour routes for the project.

Pedestrian access along the length of the project will be maintained at all times. Vehicular access will be maintained only for travel to businesses or residence within the construction area. Vehicular travel will not be allowed from the north project limits to National Ave. and points south and conversely from National Ave to W. Pierce and points further north.

Zignego Company (prime contractor), along with its sub contractors, will perform the construction on this project. The three stages of the project are listed below, with anticipated time of construction.

Stage 4 (September 2011 to November 2011)
West Greenfield Ave., 100 feet north and south of 60th St.

Stage 5 (August 2011 to September 2011)
60th St. from West Greenfield Ave. through the southern half of West National Ave.

Stage 6 (April 2011 to August 2011)
The northern half of National Ave. to the north City limits (about 200 feet north of Pierce St.) on 60th St. (National Ave will remain open until early June as an alternate route for the I-94 repaving project at which time the northern half of the intersection will be closed)

Staging, as well as exact starting and ending locations of these stages, may be modified to accommodate project needs and expedite construction.

This Web site will be updated on a regular basis with general information concerning the project as construction proceeds.