May 3, 2012

During the past week preliminary work has been occurring on the project. The contractor has been accepting delivery of pipe for the project, installing erosion control measures, and has started necessary tree removal.

On Monday May 7 (weather permitting), the contractor is scheduled to begin the pipe installation. The contractor will be starting with the installation of sanitary sewer and water main on the west side of the project along Moorland Road. As a result of this work, there will be an increase in truck traffic on Moorland Road so please exercise extra caution while traveling on Moorland Road between Grange Avenue and College Avenue.

Also on Monday, May 7, the contractor will be closing the multi-use trail on the west side of Moorland Road between College Avenue and West Ridge Drive. It is necessary to close the trail for safety reasons as the contractor will be working in close proximity to the trail. Every effort will be made to re-open the trail as quickly as possible. Please continue to check this site for updates as to when the trail will be re-opened and for updates on the completion schedule throughout the project duration.

If you have specific questions or concerns regarding this project, please contact Mr. Mike Mentzel of R.A. Smith National, Inc. Mr. Mentzel is the construction project manager and can be reached by phone at 262-317-3338 or via e-mail at mike.mentzel@rasmithnational.com.

[ Back ]

  Share this:         Copyright R.A. Smith National, Inc., 1997-